As is the case at present, all proposed generation connections, which have an installed capacity above the G83 limit, must apply for a Connection Offer under the more complex G59 connection application process.
The G59 application and quotation process includes a full technical assessment and site visit to determine the connection arrangement and any possible impact the proposed generation may have on the electricity network. Any network upgrade work required as a result of the generation installation would be chargeable to the applicant and will be detailed in our Connection Offer. Details of the G59 Connection process can be found here.