Will I need an on-site distribution substation for a new housing development?

We need to plan supply infrastructure so that we can minimise the number of substations, work out sensible routes for the cables, and maximise their use. To do that, we need to engage with developers as early as possible about the first and any subsequent phases of the development.

There is a possibility that the supply could come from an existing substation which is nearby and happens to have spare capacity.

If there is no suitable existing substation, you should start planning where to put a new substation at the outset. If there are to be other building projects on adjacent land, the most rational solution may be to share a substation with a neighbouring developer.

As each connection is unique, offering individual engineering challenges please get in contact with the design Engineer to discuss site specific conditions.