A detailed load breakdown will be required for NIE Networks to study the impact your connection will have on the network and the supply of other customers.
In order for us to carry out motor start studies we will require details of any proposed Motors >4.5kW 3ϕ to be installed. This must include:
1. Rating of Motor in kW
2. Starting current
3. Type of Motor start method e.g. Direct on line, Electronic Soft start, VSD etc.
4. Estimated number of starts per hour
NIE Networks will need confirmation on all non-liner or abnormal loads as a further detailed assessment may be required.