Even if you decide to get an ICP to undertake the contestable works there will still be involvement with NIE Networks to complete the connection. NIE Networks will complete the non-contestable works and liaise with your appointed ICP to coordinate commissioning and energisation of the contestable works. In addition, NIE Networks will be undertaking inspections of the contestable works.