Skip to main content

Overhead Line to a new house connecting to an exisiting overhead line

NIE-Works-03.png

  • New work on existing assets (installing a new cross arm and stays on the existing pole) is non-contestable
  • Constructing the first span of overhead line from the existing pole to the first new pole is non-contestable
  • Any reinforcement work needed upstream of the Point of Connection is non-contestable
  • Installing the new line (excluding the first span), new transformer and the proposed service cable is contestable work
  • Trenching on public property is contestable work