What is the difference between stage 1 and stage 2 G83 applications?

    The stage 1 application process is for single G83 installations. The vast majority of microgeneration is installed at single sites and the installer should complete a G83 stage 1 commissioning pack.

    The Stage 2 application process covers the connection of multiple SSEGs at domestic or business premises (other than within a single Customer’s Installation) in a ‘Close Geographic Region’, under a planned programme of work. In the case of projects where the proposal is to install multiple SSEGs in a number of Customers Installations in a ‘Close Geographic Region’, the Installer shall discuss the installation project with NIE Networks at the earliest opportunity. NIE Networks will need to assess the impact that these connections may have on the network and specify conditions for connection.