Skip to main content

When will I need to pay for my connection?

Initially you will need to pay the cost for your connection application fee only. We will then send you out a quote for the cost of your connection. If you accept the quote (within 90 days) then a deposit must be paid (within 90 days) for us to continue to process your application. The final balance will be required before construction commences.