Skip to main content

Once we receive an application for a renewable connection, a connection offer is issued within 90 days, provided all the necessary information has been received. The applicant has a further 90 days to accept the connection offer.

We will offer a feasibility study as an alternative to the full application process. Applicants may consider undertaking a feasibility study prior to submitting an application to the planning department for the renewable site, however full planning permission is no longer required to submit a generation connection application.